Biomedical Engineering Design Projects

Mist Generator

Skip navigation (Access key: S)
Contact information


Table of Contents


Project Overview

OMRON MicroAir Ultrasonic Nebulizer

Return to Contents


Project Status

Progress Report Archive.

Return to Contents


Project Timeline

Week Reporting Period Beginning Activities
1 January 23 formed teams, selected project, contacted client
2 January 30 literature search; met with client
3 February 6 developed understanding of project; started to develop PDS
4 February 13 brainstorming
5 February 20 evaluated three possible designs
6 February 27 worked on presentations
7 March 5 PowerPoint slides on website by 10:00 am; website up to date
8 March 12 decided on final design; handed in written report including PDS and design notebook
9 March 19 worked on design
10 March 26 worked on design
11 April 2 worked on design
12 April 9 worked on design
13 April 16 worked on final poster presentation
14 April 23 final poster presentations
15 April 30 handed in written report and notebook, final meeting with advisor

Return to Contents


Presentations and Reports

ppt icon Mid Semester Presentation (Mar 4 2004, 814 kb)
doc icon Product Design Specification (Mar 5 2004, 36 kb)
doc icon Mid Semester Report (Mar 12 2004, 564 kb)
doc icon Final Report (May 5 2004, 665 kb)
doc icon Final PDS (May 5 2004, 35 kb)
ppt icon Final Poster Presentation Powerpoint (May 5 2004, 192 kb)

Return to Contents


Contact Information

Project Team

Project Advisor and Client

Return to Contents


Valid XHTML 1.0!
Valid CSS!
Bobby WorldWide approved!
Labeled with the Internet Content Rating Association.
Owner: Willis Tompkins, Ph.D.
Author: Jon Cappel
Created: Feb 6 2004
Content updated: May 5 2004

Back to navigation bar (Access Key: N)
Back to top.