To design a leg ergometer to be used by William Schrage in his research. The ergometer will allow subjects to maintain a constant kicking motion while their femoral artery is being imaged using an ultrasound. Using the information provided by the ergometer, Schrage will determine the blood flow in the leg during exercise.

From left to right: Lein Ma, Deborah Yagow, Lacey Halfen, Laura Bagley, and Amy Weaver
Assembly of the leg ergometer is complete. The resistance device with the servo motor and brake work to provide different levels of resistance. A sensor outputs kick rate to PowerLab. A force transducer and a new crank arm must be brought/made before the project can be delivered to the client.
| Week | Reporting Period Beginning | Activities |
|---|---|---|
| 1 | September 7 | Choose team and project, meet with advisor and client |
| 2 | September 14 | Background research, preliminary design ideas, begin work on PDS |
| 3 | September 21 | Continue background research, complete and post PDS |
| 4 | September 28 | Brainstorm alternate designs |
| 5 | October 5 | Develop design alternatives for resistance device and sensors |
| 6 | October 12 | Decide on design alternatives, work on mid-semester presentation and report |
| 7 | October 19 | Give mid-semester presentation, finalize and turn in mid-semester report |
| 8 | October 26 | Decide on final design, order parts |
| 9 | November 2 | Work on final design, purchase remaining parts |
| 10 | November 9 | Continue work on final design |
| 11 | November 16 | Continue work on final design |
| 12 | November 23 | Perform tests on final design, determine and make adjustments |
| 13 | November 30 | Finalize design and final presentation, begin work on final paper |
| 14 | December 7 | Give final poster presentation, finalize and turn in paper |
| 15 | December 14 | Final meeting with advisor |
| Preliminary PDS (Oct 5 2007, 18 kb) | |
| Mid-Semester Presentation (Oct 19 2007, 3920 kb) | |
| Mid-Semester Report (Oct 24 2007, 491 kb) | |
| Final Presentation (Dec 7 2007, 2804 kb) | |
| Final Report (Dec 12 2007, 625 kb) |