Our project is to design a support for a primate transport cage that allows scientists to return primates to their respective cages.
Our final product in use:
| Week | Reporting Period Beginning | Activities |
|---|---|---|
| 1 | September 3 | Formed group, selected project, individuals selected role on team, contacted client |
| 2 | September 10 | Met with client, assessed project, brainstormed possible designs |
| 3 | September 17 | Worked on Product Design Specifications (PDS), finalized possible designs |
| 4 | September 24 | Attended Team Dynamics lecture, met with client to take pictures, began Project Builder web page, researched possible materials |
| 5 | October 1 | Chose designs on each team, began to work on mid-semester presentation |
| 6 | October 8 | Chose final design, finished mid-semester presentation, presented designs, began to work on mid-semester report |
| 7 | October 15 | Finished mid-semester report |
| 8 | October 22 | Researched materials, researched methods needed to construct our design |
| 9 | October 29 | Met with client to discuss final design |
| 10 | November 5 | Contacted mechanic, began construction of prototype |
| 11 | November 12 | Made final measurements to finalize design details, worked with mechanic to finish prototype |
| 12 | November 19 | Began testing prototype, made small alterations to prototype |
| 13 | November 26 | Continued testing design, began to work on final poster presentation |
| 14 | December 3 | Presented final design and prototype, wrote final report on project |
| Mid-semester Presentation (Oct 7 2004, 1308 kb) | |
| Mid-Semester Report Paper (Oct 15 2004, 168 kb) | |
| Final Presentation (Dec 6 2004, 2952 kb) | |
| Product Design Specifications (Dec 7 2004, 16 kb) | |
| Final Report (Dec 7 2004, 410 kb) |