Project Overview

Design a phantom for use in an MR imager to calibrate T2 relaxation value to water concentration in a gel over a range of 70 - 90%.

Pictures of a MR phantom currently used in the UW Department of Radiology for an alternative purpose:

MR Phantom (Side View)

Final Design

Prototype

Return to Contents


Project Status

Team Photo

Team Photo

Pictured from left to right: Can Pi, Missy Haehn, Laura Sheehan, and Andrea Zelisko

Progress Report Archive.

Return to Contents


Project Timeline

Week Reporting Period Beginning Activities
1 January 21 Selected Project, assigned team roles, emailed client
2 January 28 Met with Client, researched topic, started brainstorming, wrote Product Design Specifications (PDS)
3 February 4 Continued with background research, brainstormed design alternatives, started midsemster PowerPoint and paper
4 February 11 Finished background research, met with Ernie Madsen to learn about MR phantom composition and construction, developed design ideas, made PowerPoint presentation
5 February 18 Gave midsemester presentation, met with client to obtain feedback, revised PDS, wrote midsemester paper
6 February 25 Finished midsemester paper, brainstormed construction ideas, finalized design, determined amounts of supplies needed
7 March 4 Started final design drawings, ordered materials for prototype, determined receipes for samples, worked on setting up training on the relaxometer
8 March 11 Received materials, met with client, ordered additional supplies, assigned construction roles
9 March 18 Prepared samples, tested various tubes on MR imager, researched construction methods, received materials
10 March 25 Spring Break
11 April 1 Calculated T2 value of MR scan using MatLab, prepared additional Gd samples for testing, analyzed the data collected from the MR scan, worked on stair design, tested vials for water seal quality
12 April 8 Tested final concentrations of Gd samples, researched on sealing material, tested HDPE, calculated collagen and GAG values for articial disk samples, finalized the stair design.
13 April 22 Created new design to fasten the stair structure, tested final concentrations of Gd samples in relaxometer, prepared artificial disk and doped-water samples, tested the phantom prototype in the MR scanner
14 April 29 Completed and printed our design poster, stablized stair structure with epoxy, obtained more glass vials, analyzed data from prototype testing
15 May 6

Return to Contents


Presentations and Reports

ppt icon MidSemester Presentation (Feb 18 2005, 2698 kb)
pdf icon Product Design Specifications (PDS) (Feb 18 2005, 99 kb)
pdf icon MidSemester Paper (Feb 25 2005, 91 kb)
pdf icon Final Presentation Poster (May 2 2005, 4289 kb)
pdf icon Final Paper (May 4 2005, 298 kb)

Return to Contents


Contact Information

Project Team

Project Advisor and Client

Return to Contents


Valid XHTML 1.0!
Valid CSS!
Bobby WorldWide approved!
Labeled with the Internet Content Rating Association.
Owner: Willis Tompkins, Ph.D.
Author: Andrea Zelisko
Webmaster: Andrew L. Wentland
Created: Feb 4 2005
Content updated: Sep 6 2005