Project Statement: To design a device that can constantly monitor the pH levels of the bathing medium for bovine embryos inside an incubator. This device cannot alter the incubator in any way. It must also be able to accurately measure the pH within tenths of a pH level.
Different Components of the Project:
Product Design Specification:
Version 4 (April 22, 2001)
Version 3 (April 15, 2001)
Version 2 (April 1, 2001)
Version 1 (February
13, 2001)
Our probe is here, and our stand is built. If you would like to see the progress through out the semester, the following are the group's progress reports:
GROUP PROGRESS REPORTS (Each about 10 KB, PDF files):
Progress Report
1 (1-30-01)
Progress Report 2 (2-07-01)
Progress Report 3 (2-13-01)
Progress Report 4 (2-21-01)
Progress Report 5 (2-28-01)
Progress Report 6 (3-06-01)
Progress Report 7 (3-21-01)
Progress Report 8 (3-28-01)
Progress Report 9 (4-04-01)
Progress Report 10 (4-11-01)
Progress Report 11 (4-18-01)
Progress Report 12 (4-25-01)
Progress Report 13 (5-02-01)
Project Schedule: Week Date Design Activities
Week 1 (1/31) Meet with client
Week 2 (2/2 - 2/9) Gather research
Week 3 (2/9 - 2/16) Gather more research and ask client questions
Week 4 (2/16 - 2/23) Come up with ideas for design and write outline
Week 5 (2/23 - 3/2) Complete the Report and Slides for the Presentation
Week 6 (3/2 - 3/9) Meet with the client and discuss our design ideas
Week 7 (3/9 - 3/23) Break into small groups to begin final design
Week 8 (3/23 - 3/30) Meet with client, form list of needed items and break into small groups for the building phase
Week 9 (3/30 - 4/6) Design stand, begin writing paper, talk to companies about ordering parts
Week 10 (April 6) Stand group continued to design stand, companies contacted, paper started
Week 11 (April 13) Stand group finalized the design, talked to Bill at the shop. Client meeting to finalize the ordering of the probe. Paper group started getting specifics from the different groups, researching ethics.
Week 12 (April 20) NO CLASS - ENGINEERING EXPO; continued
individual work in groups.
Week 13 (April 27) Finalize design, building stand, initial testing, put together slides for presentation.
Week 14 (May 4) FINAL PRESENTATIONS; PAPER DUE
Week 15 (May 11) Final Meeting with Advisor: Friday 12:30pm
Week 16 (May 14-18) DONE!
Final Presentation Slides [zipped Powerpoint 2000, 510 kB]
Final Paper [Adobe PDF, 1.5 MB]
-----------------------------------------------
Midsemester Presentation Slides [zipped Powerpoint 2000, 136 kB]
Midsemester Paper [Adobe PDF, 84 kB]
Group Members:
Team Leader: Mike Swift
Communication Leader: Ryan Porter
Webmaster: Sara Alford
BSAC Representative: Gabriel Martinez-Diaz
Byoung Choe
Steve Huffacker
Laura Wing
Kristi Hinner
Carla Maas
Client:
Theresa Duello
Associate Professor
Obstetrics and Gynecology
5240 Medical Sciences Center
tmduello@facstaff.wisc.edu
Advisor:
Nimmi Ramanujam
278 CAE
nimmi@engr.wisc.edu