Skip navigation (Access Key: S).
| From: | Paul Thottakara |
|---|---|
| Sent: | Tue, 30 Apr 2002 11:59:20 |
| To: | Willis Tompkins |
| Cc: | Andrew Hoyord; Miroslav Backonja; Paul Victorey; Bern Jordan; Dana Mueller; Paul Thottakara |
| Subject: | BME 402 Progress Report |
Andrew Hoyord
Bern Jordan
Dana Mueller
Paul Thottakara
Paul Victorey
Miroslav Backonja
5/1 - 5/7
"Doctors are now finding it necessary to test patients experiencing pain or numbness primarily in their extremities, and possibly the trunk or face for neurological damage and warm/heat sensitivity by applying hot sensations to their skin. A device that heats up to target temperatures of 38 and 45 degrees Celsius relatively quickly, and is portable, allowing the doctor to carry it between examining rooms. The first prototype is being designed to run off regulated voltage from a wall outlet.
Past
12/7 - 12/20: Wrote final paper and poster presentation. Final meeting with
advisor.
1/23 - 1/29: Start of new semester. Soldered components to two PCBs. Contacted
client.
1/30 - 2/5: Ordered remaining components for board(power transistor, case).
Completed construction of the two boards. Began testing the boards.
2/6 - 2/12: Redesigned probe head to allow mounting on project case. Ordered
remaining components neccesary for first prototype completion.
2/13 - 2/19: Met with client. Reviewed and filled out some of the material neccesary
for HSC application.
2/20 - 2/26: Machined probe heads. Submitted IDR to the WARF. Began computer
drawing of prototype.
2/27 - 3/5: Ordered remaining hardware neccesary for the construction of our
probe. Set up meeting with HSC representative. Completed project box layout.
3/6 - 3/12: Machined project box and PVC coupling for probe attachment.
3/13 - 3/19: Midsemester presentation. Met with representative from the WARF.
Finished machining the project box. Tested thermistors. Began construction of
new probe heads.
3/20 - 4/2: Began testing of new probe heads. Plotted temperature waveform of
our STAMP while operating. Spring Break (3/23 - 4/1)
4/3 - 4/9: Worked on new heating routine. Determined could not write journal
by deadline.
4/10 - 4/16: Worked on a heating routine using changing duty cycles to regulate
temperature. Found liquid crystal supplier. Developed way to fasten Ni-Cr wire
leads without soldering.
4/17-4/23: Created new attachment after epoxy found in the threads of the old
one. Finished new version of code with threshold control implemented. Attached
Ni-Cr leads with modified screws.
4/23-4/30: Continued construction of the prototype, almost complete.
5/1-5/7: Finished epoxying switches to project box, worked more on the safety
features of the code.
Future
5/8 - 5/14: Extensive testing of prototype I. Make modifications and enhancements
to prototype I as needed. Finish writing journal article. Work on Final Presentation.
Meet with Client. Final presentation.
5/15-5/17: Final meeting with our advisor.
Unable to work in the BME lab during the day this week, because EMA has
reserved the lab for meetings
WARF has decided not to pursue a patent for our device.
Have not been able to get any further response from liquid crystal distributor.
| Andrew: | BSAC meeting | 2.0 hours |
|---|---|---|
| Bern: | BWIG, talking to teachers at Middleton HS about outreach | 3.0 hours |
| Dana: | Communication with Liquid crystal company and client, updating design notebook | 3.0 hours |
| Paul T: | Updating design notebook | 3.0 hours |
| Paul V: | Group work | |
| Group: | In Class Meeting (5/3/02) - Epoxied switches to project box, worked on safety features of the code | 2.0 hours |
9.5 hours
209.5 hours