| January | 25 | First class meeting. Teams are constructed and projects distributed. |
| February | 1 | Meeting with Prof. Thesen in his office at 2.30pm. Discussion about the expectations and scope of the project. |
| 4 | First meeting with client at Pleasant Company DeForest site | |
| 8 | Group meeting with Prof. Thesen in his office at
2.30pm. Web-page will be evaluated. |
|
| 11 | Second field trip to Pleasant Company,
DeForest site. Research continuation. |
|
| 13 | Group meeting at CAE computer lab. | |
| 15 | Class meeting. Present proposal. Completed. Update webpage. | |
| 16 | Group meeting at Mech. Engr. lobby. | |
| 22 | Group meeting with Prof. Thesen in his office at 2.30pm. Work on project. Web-page will be evaluated. |
|
| 25 | Field trip to Pleasant Company, Middleton Site. Research continuation. |
|
| 28 | Meeting with Pat Rebholz to go over design sketches. | |
| 29 | Group meeting with Prof. Thesen in his office at 2.30pm. Write best practices report. Update webpage. |
|
| March | 5 | Group meeting at CAE computer lab. |
| 6 | Meeting with Pat Rebholz at Milan,
Johnson St. Go over design ideas. |
|
| 7 | Class meeting. Present best practices. Completed. Web page will be evaluated. | |
| 14 | SPRING RECESS!!! SPRING RECESS!!! SPRING RECESS!!! SPRING RECESS!!! | |
| 21 | Design and evaluation | |
| 24 | Meeting with Pat Rebholz at Pleasant Company, Middleton Site. Design and evaluation |
|
| 27 | Meeting at Pleasant Company, DeForest Site. Design presentation to management. Completed. |
|
| 28 | Meeting at Pleasant Company, DeForest Site. Design presentation to operators. Completed Group meeting with Prof. Thesen in his office at 2.30pm. Udate we-page. Web-page will be evaluated. |
|
| April | 4 | Design and evaluation |
| 11 | Class meeting. Present Progress to
date. Completed. Write
report. Update web-page. |
|
| 13 | Group meeting at Union South study
lounge/lobby. Project discussion and work delegation. A rough draft of the final report will be available tentatively late Monday. A meeting on Monday is also scheduled. |
|
| 17 | Group meeting at Mechanical Engineering lobby. | |
| 18 | Group meeting with Prof. Thesen in his office at 2.30pm. Draft of report due (Optional). Completed. Web-page will be evaluated |
|
| 24 | Meeting with Pat Rebholz at Pleasant Company, Middleton
Site. Draft of final report is evaluated by Pat Rebholz. |
|
| 25 | Group meeting at 2nd floor Mechanical Engineering. Final report revision. |
|
| 27 | Group meeting. Final report and final presentation revision. |
|
| 28 | Final presentation to sponsor. Completed. | |
| May | 2 | Web-page will be evaluated. Peer evaluations due. |
| 9 | Class meeting. Final presentation. Final report due. Completed!!! |